CS605
Quiz NO 3
Prepared by Amna
100% correct solution
Fall 2023
1. Formula
for total number of Channels of communication involving N people is given by
N * (N-1) /
2
2. The basic
principle is that the review should focus on the
product
and not the producer
3. CPM
stands for
critical path method
4. Schedule
performance index is equal to
SPI
= BCWP/BCWS
5. Only ________________
of the software components scheduled for reuse will, in fact, be integrated
into the application
70%
6. Identify
the degree of uncertainty that the product will meet its requirements and be
fit for its intended use
Performance
risk
7. BCWS
is a term in earned value analysis it stands for
Budgeted Cost of Work
Scheduled
8. ___________is
another very important quality factor and is defined as probability of failure
free operation of a computer program in a specified environment for a specified
time.
Software
reliability
9. FTR
stands for
Formal Technical Review
1 CPM is a technique which helps us in
preparing a schedule for the project, it stands for
Critical
path method